Question 51

MCQ · Single Correct 1 mark

In Barry Boehm's COCOMO model, what standard size metric is used as the primary effort estimation input parameter?

Answers for question 51

Question 52

MCQ · Single Correct 1 mark

In basic COCOMO, which project mode represents small, simple software projects developed by experienced teams with flexible requirements?

Answers for question 52

Question 53

MCQ · Single Correct 1 mark

In Allan Albrecht's Function Point Analysis (FPA), which category represents data files generated and maintained completely inside the software application boundary?

Answers for question 53

Question 54

MCQ · Single Correct 1 mark

What project management technique determines the minimum total project completion time by identifying the longest continuous path of dependent tasks with zero float?

Answers for question 54

Question 55

MCQ · Single Correct 1 mark

In PERT three-point estimation, what formula calculates the Expected Duration (Te) given Optimistic time (to), Most Likely time (tm), and Pessimistic time (tp)?

Answers for question 55