Question 16

MCQ · Single Correct 1 mark

Which GoF structural design pattern dynamically attaches additional responsibilities to an object at runtime as an alternative to subclassing?

Answers for question 16

Question 17

MCQ · Single Correct 1 mark

In project management, what project scheduling diagram represents project activities as nodes connected by arrows to determine activity dependencies and critical paths?

Answers for question 17

Question 18

MCQ · Single Correct 1 mark

In Critical Path Method (CPM), what is defined as the sequence of dependent project tasks that determines the absolute minimum total duration required to complete the project?

Answers for question 18

Question 19

MCQ · Single Correct 1 mark

In PERT estimation, if Optimistic time is $T_o$, Most Likely time is $T_m$, and Pessimistic time is $T_p$, what is the formula for calculating Expected Duration ($T_e$)?

Answers for question 19

Question 20

MCQ · Single Correct 1 mark

What project management term describes the total allowable time an activity can be delayed without delaying the overall project completion date?

Answers for question 20